of a typical residential project 200m2 ~ 300m2 in an approved plot of land.
A rough estimation we would say is min.14 ~ max.24 months.
Usually the design takes between one (1) to four (4) months.
The planning permission takes between one (1) to two (2) months.
The Building permission between one (1) to two (2) months.
Tendering action & evaluation one (1) to two (2) months.
The actual construction ten (10) to fourteen (14)